We spent time with family for Christmas but had lots of time to work on projects too. We installed the vent for the master bath when it was too cold and wet to be outside and worked on grading and putting in a short retaining wall when it was dry and sunny.
Regular status updates of on the progress of our remodel. Our goal is to turn a 1950s era home into an energy efficient, attractive home suitable for the next generation.
Sunday, December 27, 2015
Sunday, December 20, 2015
Step by step
Another weekend and more slow progress. Saturday was relatively dry and we did some work on the west side yard. Specifically we worked on some grading and retaining wall construction. Today was wet and worked on the vent fan setup in the master bath. Progress was very slow, but I got the fan unit mounted and got some layout stuff done. It took a long time to get things mounted at a 53 degree angle. Another day and another project.
Sunday, December 13, 2015
Bathroom vent
We've been on an epic quest to purchase duct from our local big box store. We ended up buying a few sections from an awesome local hardware store. We try to buy local as much as possible, and wish the local stores would be open weekends and Sundays.
Sunday, December 6, 2015
Passed our rough electrical inspection!
One more major milestone down. The inspector asked several questions, and Ian was prepared for every one. No punch list. He was complementary of all the work we had done.
Now on to low voltage for internet and a security system.