Sunday, December 27, 2015

Duct the halls!

We spent time with family for Christmas but had lots of time to work on projects too.  We installed the vent for the master bath when it was too cold and wet to be outside and worked on grading and putting in a short retaining wall when it was dry and sunny.

Sunday, December 20, 2015

Step by step

Another weekend and more slow progress.  Saturday was relatively dry and we did some work on the west side yard.  Specifically we worked on some grading and retaining wall construction.  Today was wet and worked on the vent fan setup in the master bath.  Progress was very slow, but I got the fan unit mounted and got some layout stuff done.  It took a long time to get things mounted at a 53 degree angle.  Another day and another project.

Sunday, December 13, 2015

Bathroom vent

We've been on an epic quest to purchase duct from our local big box store.  We ended up buying a few sections from an awesome local hardware store.  We try to buy local as much as possible, and wish the local stores would be open weekends and Sundays.

Sunday, December 6, 2015

Passed our rough electrical inspection!

One more major milestone down.  The inspector asked several questions, and Ian was prepared for every one.  No punch list.  He was complementary of all the work we had done.

Now on to low voltage for internet and a security system.

Sunday, November 22, 2015

Home Runs!

No, not baseball.  The home run is the wire that runs back to the panel.

And the sunset from our master bedroom.  Ahhh....

Monday, November 2, 2015

November is Here

We continue to move forward step by step.  This weekend we finished another bedroom and also finished the conduit for the "large" circuits.  In hindsight it probably would have been more reasonable to just use large gauge Romex wire instead of conduit.  Regardless, the work is done now and is how things are going to be.

The end for the rough electrical is in sight and hopefully we pass our inspection the first time.

Sunday, October 25, 2015

We're back!

We took a bit of a break for a few weeks.  Ian had a trip out of the country and I spent my weekends catching up on other things.  We got back to it this weekend and got the playroom and stairway wired.  Only a few rooms left before we can get the rough electrical inspection.

Saturday, October 24, 2015

How to get a box in an impossibly small space

Use a wide chisel as a hammering surface when there isn't enough space to hammer directly.

Sunday, October 4, 2015

Shallow new work boxes

We hunted all over the internet and couldn't find a good examples of how to install electrical in the shallow framing around our basement wall.

We used carlon new work boxes.  They are single gang boxes, but double gang wide so they have 18 cu in capacity.  To safely secure the romex, we used EMT conduit.  The EMT keeps the romex in place and protects it from damage during sheet rock install.  Make sure to use the plastic bushings so that the end of the EMT is smooth and won't cut the romex.

We weren't sure how to use the knockouts on the boxes because they are different than the rest of the Carlon line.  Just push, and the plastic flexes out of the way.

Monday, September 28, 2015

Soundtrack for my remodel

We listen to a lot of music as we work.  Sometimes I think about the slideshow that I'll show to guests in the future and I hear "Anna Son" by Walk the Moon playing in the beginning.  We're rattling this ghost town.  When we're finished, and showing the completed photos I imagine  "Let's be Still" by Head and the Heart.  Some times in this project, the world is turning a little too fast and we aren't taking enough time to pause.  Yesterday as we were working on electrical "Burning Down the House" by Talking Heads started playing.  Definitely not part of the chosen soundtrack.

Saturday, September 26, 2015

Armored cable

We wired light boxes near an attic access.  The cables need to be in conduit or protected within 6 feet of attic access.  Ian's discovery in the process: armored cable is not symmetrical, so the screw in connectors are really easy on one end and much harder on the other. 

Sunday, September 20, 2015

How to nail up a round light box

My husband suggested that as I learn new skills, I blog about how I do things.  Maybe it will be helpful to someone else.  I used to hate nail in boxes, they come with a lip that spaces them sort of right if you are going to have 3/8 in sheet rock.  But we're planning on 1/2 inch and boxes that are too shallow are a fire hazard.  So, here's my process:

1.  Measure and mark the center of your box.  I had to adjust due to the framing.  This is a closet light that can be a little off center.

2.  Measure the spacing of the nails, both horizontal and vertical (see photo).

3.  Mark where the nails should go, in my case 4 1/2 in apart and 3/4 in back.  (See photo). 

4.  Start to hammer and make sure you are hitting your marks.  Hold the box tight to the board.  You may have to check, and if you're off start the other nail (so that your nail doesn't pull back in the bad hole) , then try again.

5.  Once both nails are started, use a small level to hold the box straight as you nail.  (See photo)

6.  And nail till your box is secure.  In my example, I should have given myself about 1/4 more space on the left.  My hammer head didn't clear.  This took some creative (and not recommended) hammer work to get the nail in.  But the job is accomplished.

Friday, September 18, 2015

You load 16 tons...

Not quite 16, more like a ton and a half.  We worked on the drainage in an area in front of the house that once was a planter.  We also backfilled the drainage in front of this wall.  Something that our contractor should have done, but never did.  It feels good to have one less open trench.

Monday, September 7, 2015

Wires, wires everywhere.

The garage is wired.  The powder room is wired.  The front bedroom is wired.  The master bath is mostly wired.  We are making progress and far exceeded what we expected to get done this weekend.

Front Bedroom Wired

We completely wired the front bedroom/ home office.  On to the master bath.

Saturday, September 5, 2015

Wiring for window openers

We did want to have to get up on that ladder each time we needed to open it close our clearstory windows, so we ordered openers and just got the low voltage wiring in to control them.

Friday, September 4, 2015

Ceiling electrical boxes

I've mounted boxes as Ian drilled holes for the cables.  The key to mounting the boxes is to measure exactly where the mounting nails should go.  This helps me make sure I leave the right gap for the sheet rock.

Vent in bathroom

Last week, I forgot to blog, but we got a lot of wiring done.  So far today on our labor day work-a-thon we've installed a bathroom fan. 

Sunday, August 23, 2015

Sheet rock chases!

Ian built a sheet rock chase to surround one of our vents.  We're going to end up with a nice built in cupboard in front of the vent.  I helped with a lot of wiring and vacuuming.

Sunday, August 9, 2015

Bite from the elephant

More work this weekend on the upstairs electrical.  It doesn't look much different, but it is progress. 

Sunday, July 26, 2015

The Saga Continues

We dealt with odds and ends around the house.  Electrical, plumbing, etc.  Nothing monumental, but all in the right direction.

Sunday, July 19, 2015

Pulling Wire

Until today we just setup a makeshift stand every time we needed to pull wire.  I realized that there was still a lot of wire to pull so I took a little bit to build a jig to help hold the spools while we pull wire.  I am happy with the result.  The pulls today were A LOT easier.


Saturday, July 18, 2015

Disconnect

Today we ran conduit for the electrical for our hot water heater.

Ammenities

Over the last two weekends, we've been focused on getting some basic amenities.

Saturday, June 27, 2015

Bathtub!

I was afraid it wouldn't fit. But it does! The plumber was here today and worked on rough plumbing. Ian's dad leveled the floor and we mounted a door and did more work on electrical.


Saturday, June 20, 2015

More lights and framing

Today Ian's dad fixed framing so that our shower valves can go in the right place. Ian and I worked on installing lights and outlets in the downstairs storage area.

Sunday, June 14, 2015

Plywood

Today we worked on putting plywood over the old subfloor. The floor feels so stable now. Lots of screws. No more squeaks!

Saturday, June 13, 2015

Let there be lights

Ian and I spent the last two days continuing to work on kitchen electrical.  All the lights are in and rough wired. 

Walt spent the last two days keeping water and dry land separated....  He backfilled over the water service with sand, then magnetic marking tape (spray painted blue, because we couldn't find the water marking tape in stock), then to original grade and tamped to compact.  The picture doesn't look amazing but after months of an open trench cutting through my yard, I'm so thankful. 

We all said it was good.  And there was evening and there was morning...

Sunday, May 31, 2015

More wiring

More circuits wired this week.  My accomplishment for the weekend was installing the red clips which control electrical cables, per code and keep multiple cables safely away from where they might get hit with a nail during Sheetrock installation.

Sunday, May 24, 2015

Ready to have water reconnected.

Trenching for our water service.  The yellow line is our gas service.  It's a good thing we called for an underground service alert. 

Friday, May 22, 2015

Insulation!

It's supposedly safe to be here now.  Still a slight odor.  It seems quieter even though there is still no insulation in the walls.